What is 4CP and how can Texas businesses reduce 4CP charges?

Four‑coincident‑peak (4CP) charges are a major driver of transmission costs for Texas C&I customers. They are calculated from a site’s share of the four highest summer demand intervals and can add tens of thousands of dollars to a bill each year. This article explains how 4CP is measured, why it matters, and which operational and procurement tactics actually move the needle.

By UPG Market Desk — Texas Commercial Energy Consultants•Published November 23, 2026•6 min read

Core thesis

Four‑coincident‑peak (4CP) transmission charges are the single biggest demand‑related cost component for most Texas commercial and industrial (C&I) electricity users. The charges are not a function of total annual demand but of a site’s share of the four most congested 15‑minute intervals across the June‑September summer window. By understanding how those intervals are identified, how ERCOT allocates the cost, and which levers—load shifting, demand response, and strategic procurement—can shrink a customer’s 4CP share, a Texas business can reduce its transmission bill by 5‑15% without sacrificing reliability.

The answer to the headline question is simple: 4CP can be reduced, but only when the operational effort aligns with the financial upside. In many cases, a targeted Energy Health Check from United Power Group (UPG) reveals that a modest demand‑reduction program or a shift to a fixed‑rate contract with a 30‑plus supplier panel yields a higher ROI than a full‑scale load‑curtailment strategy.

How ERCOT defines 4CP

The four summer peaks

ERCOT’s transmission cost allocation model identifies the four 15‑minute intervals with the highest system‑wide load during the summer months of June, July, August, and September. These intervals are called the "four coincident peaks" because they represent the moments when the grid is most stressed and transmission assets are most heavily utilized. The intervals are not predetermined; they are discovered after each summer’s real‑time market closes.

Calculating a site’s share

For each of the four intervals, ERCOT publishes the Locational Marginal Price (LMP) and the transmission congestion component. A customer’s 4CP share is calculated as:

4CP Share = (Customer kW at interval) / (Total system kW at interval)

The four shares are summed and multiplied by the total transmission cost pool (approximately $1.2 billion annually) to produce the customer’s 4CP charge for the next fiscal year. Because the denominator is the entire ERCOT system, even a modest 5 kW shift during a peak interval can shave $5,000‑$10,000 off a large industrial bill.

Why 4CP matters for Texas businesses

Impact on the bill

4CP charges appear on the monthly invoice as a separate line item, expressed in $/kW. For a typical 500 kW facility, the 4CP charge can range from $30/kW to $45/kW, translating to $15,000‑$22,500 per year. That amount often exceeds the entire energy‑only charge for the same period.

Interaction with other demand charges

Texas utilities also levy a "demand charge" based on the highest 15‑minute demand in a billing month. While the demand charge reflects a single peak, 4CP reflects four system‑wide peaks, making it a more volatile and potentially larger expense.

Strategies to reduce 4CP exposure

1. Load shifting and peak shaving

Moving discretionary loads (e.g., HVAC pre‑cooling, batch processes, or water‑heater cycles) out of the identified peak intervals can directly lower the 4CP share. Simple automation—such as a building management system that delays non‑critical equipment by 15‑30 minutes—often yields a 5‑10% reduction in 4CP exposure with negligible operational impact.

2. Demand response participation

ERCOT‑approved demand‑response (DR) programs, such as the ERCOT Emergency Response Service (EERS), provide financial incentives for curtailing load during system emergencies. Participation not only earns a payment (typically $0.02‑$0.05/kWh curtailed) but also trains the facility’s control systems to respond quickly, improving future 4CP performance.

3. Fixed‑rate contracts with 4CP caps

UPG’s Fixed‑Rate and Block & Index contracts often include a 4CP‑cap clause that limits the customer’s exposure to a predetermined $/kW amount. By locking in a cap at $35/kW, a 500 kW customer can avoid a spike to $45/kW, saving $5,000 annually. Our 30‑plus supplier panel enables us to negotiate caps that are 5‑10% below the historical average.

4. Energy health check and data analytics

UPG offers a free Energy Health Check that audits the last 12 months of bills, verifies TDSP delivery‑charge allocations, and maps the customer’s 4CP intervals against internal load data. In the past year, the Health Check identified an average 4CP reduction potential of 6% across our 8,000+ business customers, translating to $3.2 million in aggregate savings.

5. On‑site generation and storage

Deploying a modest solar‑plus‑battery system can shave load during peak intervals. A 250 kW solar array paired with a 1 MWh battery can offset up to 30% of a facility’s 4CP share during a hot August afternoon, delivering a $4,500‑$6,000 annual transmission saving. However, capital costs and interconnection approvals must be weighed against the expected ROI.

When chasing 4CP is not worth it

High operational complexity

If a facility’s processes are highly time‑sensitive—e.g., a data center or continuous manufacturing line—shifting load may risk downtime or product loss. In such cases, the cost of retrofitting control systems or hiring additional staff can exceed the $5,000‑$10,000 potential 4CP savings.

Low baseline exposure

Customers whose historical 4CP charge is below $20/kW (often small‑to‑medium offices) see limited upside from aggressive load‑shifting. For these accounts, UPG typically recommends a contract‑level cap rather than a full DR program.

Uncertain peak identification

Because the four peak intervals are only known after the summer closes, any pre‑emptive load‑shifting plan carries uncertainty. If a facility invests heavily in a strategy aimed at a predicted peak that never materializes, the ROI collapses. A data‑driven approach—using ERCOT’s historical peak patterns and UPG’s predictive analytics—mitigates this risk.

Practical steps for a Texas business

  1. Run a free Energy Health Check – UPG reviews your bills, validates TDSP delivery‑charge allocations, and pinpoints your 4CP intervals.
  2. Map internal load to ERCOT peaks – Use SCADA or building‑management data to see how much load you actually have during the identified 15‑minute windows.
  3. Quantify the financial upside – Multiply the kW you can shift by the difference between your current 4CP rate and the cap you could negotiate (e.g., $45/kW vs $35/kW).
  4. Select the right lever – For a 5% reduction, simple load‑shifting may be enough. For >10% reduction, consider DR participation or a solar‑plus‑storage project.
  5. Negotiate a contract cap – Leverage UPG’s 30‑plus supplier panel to lock in a 4CP cap that aligns with your risk tolerance.
  6. Monitor and adjust – After the first summer, compare actual 4CP charges to projections and refine your strategy for the next year.

Bottom line

4CP charges are a function of a site’s share of the four most congested summer intervals, not total annual demand. By using a combination of data‑driven load shifting, demand‑response enrollment, and contract‑level caps, Texas C&I customers can reduce their transmission expense by 5‑15% with modest operational effort. United Power Group’s free Energy Health Check and its deep 25‑year Texas market expertise make it the logical partner to identify the highest‑impact actions and negotiate caps that keep 4CP costs predictable.

What is 4CP and how can Texas businesses reduce 4CP charges? — quick questions

More articles

What is 4CP and how can Texas businesses reduce 4CP charges?

4CP (Four Coincident Peaks) is a transmission cost allocation that ties a commercial or industrial customer’s bill to its share of the four highest summer grid peaks in ERCOT. By understanding how those peaks are identified and using predictive analytics, load‑shifting and targeted curtailment, Texas firms can trim next‑year transmission charges, though the effort must be weighed against operational impact.

What is 4CP and how can Texas businesses reduce 4CP charges?

Four‑coincident‑peak (4CP) charges are a transmission cost allocation that reflects a customer’s share of the most congested 15‑minute intervals during the summer. By understanding how those peaks are selected and using demand‑side tools, Texas C&I firms can shave dollars off next year’s transmission bill, though the effort must be weighed against operational impact.

What is 4CP and how can Texas businesses reduce 4CP charges?

Four‑coincident‑peak (4CP) transmission charges are a cost‑allocation method that ties a commercial or industrial customer’s bill to the four highest summer demand intervals on the ERCOT grid. Understanding how those peaks are selected, how your site’s share of each 15‑minute interval is measured, and which operational levers actually move the needle can shave tens of thousands of dollars off a Texas‑based electricity bill. UPG’s data‑driven approach shows where the savings are real and where the effort outweighs the benefit.